 EGR 486 Progress Report
 
 Name                 Adam W. Chan
 Date                   June 6, 1998
 Project Title      Flipper Door Change
 Sponsor             Herman Miller, Inc.

Major accomplishments since last report:

When last we left our heroes....
The table had been built to hold the flipper door template and the other machinery.  Due to an oversight on my part I had a meeting scheduled with YoungBlood to discuss grippers but it was at the same time as the Senior Project discussion so the meeting was canceled.  I have re-scheduled the meeting for Thursday so we should be able to finalize our design specifications for the grippers.  This coupled with Jeff Maxim's linkage design should be the last step in our process.  Then it's just a matter of final assembly, debug and documentation.

Major problems since last report:

IMT is still are constraint.  I have asked for an order of 5-10 "blank" flipper doors so that Aaron and I can work on a prototype design.  IMT is dragging their feet in implementing an ECO (engineering change order) to get us a prototype and send it through their testing facilities or rather the Design Yards testing lab (a Herman Miller research company).
 

Objectives for next week:

Continued assembly on the machine itself and getting the "blank" flippers to work on for a prototype. Continued documentation on machine design.